Telecom and Clear ATM for KCCS


28 April 2001
The Telecom ATM to KCCS now has twenty circuits (PVCs) installed, over the last six weeks there have been fourteen PVCs installed replacing WDDS/DEDX from stacked widebands at KC and upgrades from ISDN circuits.
Several more PVCs are due for installation early next month.
The first PVC on the Clear ATM was installed today, it is a 2meg domestic internet connection to Clear's CLIX. A further 1meg pvc to CLIX for international internet bandwidth (Southern Cross fibre cable to USA) has been ordered for installation 10May. This will be moved to 2M if tests are sucessful. Two customer PVCs of 512k each have been ordered for connection to the Clear ATM.

15 April 2001
The Clear ATM was at last fully commissioned today. The final delay was waiting on an ATM card for KC's Cisco 7507 router. The wrong type of interface card had been obtained last December (MM instead of SM). Another spare ATM controller has been ordered for delivery end April.

30 March 2001
The Clear contractors have now completed the last splice in the fibre cable to KCCS. The circuit is now being tested for a few days.

28 January 2001
There are now over twelve circuits to KCCS being moved from stacked wideband to ATM/Frame Relay. Although these were requested early December they are only now being actioned. Until now the only circuits using the Telecom ATM at KC have been international and domestic internet bandwidth from Telecom (Global GAteway), International bandwidth from Aaria, Telecom IPnet services and three new Frame Relay connections to KC customers.

20 January 2001
With the Christmas/New Year holiday just about over the contractors have ersumed work on the Clear ATM. It now appears there are several issues with termination at Queen Street which will delay complete installation for a few more weeks.
Clear have relocated their equipment to avoid problems with other circuits terminating in a PABX room. The internal connections to KC are almost complete.

28 December 2000
Clear contractors completed excavation in Queen Street to route a fibre cable into 109. This is now terminated in the basement and will be connected to Clear equipment in KC's offices early in the new year.

22 December 2000

Further connections into ATM were completed today, KC's international bandwidth from Aaria was moved from a frame relay to an ATM VC and a 2meg frame relay link to ATL was also moved to an ATM VC.
Several attempts during this week to move IPnet services to an ATM VC have failed. The IPnet services will comtinue to use a 2meg frame realy circuit installed to Titirangi. This move will be revisted after the Christmas/New Year holidays.

14-15 December 2000

The 155Mbit ATM connection from Telecom NZ was commissioned 12th December and over the next few days data circuits from Telecom Global Gateway, for international traffic, and Netgate for domestic traffic were moved to use this new circuit.
This ATM is delvered as a single mode fibre cable and connects to an ATM swith at Telecom's Mayoral Drive exchange. Telecom's Netgate and Global Gateway supply domestic and international bandwidth using Virtual circuits (VCs) over the ATM, this allows existing 2meg frame realy and a DDS link connecting into one of KC's stacked wideband DDS to be replaced.

12 December 2000

The Telecom ATM circuit is just about fully installed as the last stage of joining fibre cables in Queen Street was completed and the whole fibre circuit was tested 'end-to-end' this morning.
This has brought to an end a rather long drawn out process where multiple delays have resulted in this Telecom ATM circuit taking over five months from initial ordering to completion. Originally expected in October 2000 this near two to three month delay had caused some major problems in providing resources to KC customers and having substantial investment in ATM hardware idle over the same period.
As interim measures Telecom were able to share various frame relay circuits into KC with internal and national data connections and a major realignment of channels used on four stacked wideband DDS allowed several contiguous blocks of timeslots to be made available for new customer circuits.

11 December 2000

Clear ATM equipment arrives in KC's offices today. The first stage of installing the Clear ATM circuit was started.
The Telecom contractor is completing the last fibre cable splice today This is in Queen Street just outside 109. The only remaining task is to provide a single mode fibre cable between the Telecom junction box and the Cisco 7507 ATM controller in the Computer room

5 December 2000

On Sunday 3rd December the contractor started the footpath excavation and it was completed late Monday 4th. We now have a fibre cable into the basement of the building.
Another Telecom contractor installed some fibre termination cabinets in KC's computer room. He expects to have this all completed by 8th December.

30 November 2000

Still no ATM. The contractor has still not started the street excavation and now it appears unlikely anything will be done for another week or so. Two problems have arisen - No street work over this weekend as it is the annual 'Santa Parade' on Saturday and the Coucil require the work to be completed before December! An extension has been allowed to 4th December but confidence in actually getting this ATM circuit is quickly evaporating. :-(

20 November 2000

More delays with the ATM installation. The City Council approval for excavating the footpath was delayed apparently due to staff holidays in the Council. Now approval has been given to have the job completed by 1 December 2000 so completion is expected by 28/29th November.

20 October 2000

After some delays in processing paperwork for the ATM circuit from Telecom the expected installation date is now 10th November, this closer date was provided as it seems approval from the City council can be obtained sooner than expected.

12 September 2000

The installation of ATM was included in the agenda at a meeting with Telecom in KC's new offices (109 Queen Street) today. Apparently there was some paperwork delays within Telecom which have now been resolved and the installation is proceeding.
The next stage is with cable installation contractors who have to excavate the footpath between the BNZ tower and 109 Queen Street, a distance of about 15 metres, to connect the fibre to a junction point in the BNZ tower.

12 August 2000

As part of the move to new offices at 109 Queen Street, two ATM data have been circuits ordered, one from Telecom NZ and the other from Clear Communications. Both are due for installation in November/December. Four Telecom stacked wideband DDS and eight Primary Rate ISDN circuits have already been installed at Queen Street. A new 2meg domestic link to Telecom Netgate and a 2meg DDS to Highland Ave are also installed.

The Telecom ATM will be a 155Mbit circuit and will initially be used to connect international and domestic internet circuits to Telecom Netgate, IPnet services to Netgate and eventually ADSL services to Netgate.
Some eighteen data circuits (MDDS/DDS and DEDX) to customer sites will be moved from existing stacked wideband DDS at KCCS to frame relay circuits connecting into the Telecom ATM.

The Clear ATM will initially be a 34Mbit circuit with domestic traffic connection to Clear, frame relay connection to Aaria and initially six KCCS customer data circuits again using frame relay.

Both ATM circuits will connect to KCCS's Cisco 7507 router.

Enquires about services provided by KCCS or matters related to this move should be made to David Dix .


[ What's Happening? | KCCS home page ]

These pages designed and maintained by the KC webmaster. If you have any queries or comments about the KC World Wide Web pages or other services please contact us .

Page owner: <dgd@kcbbs.gen.nz>
Last modified: 4 May 2001.